Question: Project New Concentration at SSU work breakdown structure has outlined the following activities: Activity Predecessor Normal Time (TE) in Days A: Obtain Instructor - 7
Project New Concentration at SSU work breakdown structure has outlined the following activities:
| Activity | Predecessor | Normal Time (TE) in Days |
| A: Obtain Instructor | - | 7 |
| B: Locate a Room | A | 3 |
| C: Check Costs | - | 6 |
| D: Room Availability | C | 3 |
| E: Schedule Classes | B, D | 2 |
- Construct a AON network diagram:
- Show the ES/EF, LS/LF, and the slack for all activities
- Show the critical path ( write it out below the network)
For the next set of question s refer to the table below:
| Activity | Crash Time (in days) | Crash Cost (total) | Normal Time (TE) in Days | Normal Cost (total) | Crash Cost per day |
| A: Obtain Instructor | 4 | $ 800 | 7 | $ 500 |
|
| B: Locate a Room | 2 | $ 350 | 3 | $ 200 |
|
| C: Check Costs | 4 | $ 900 | 6 | $ 500 |
|
| D: Room Availability | 1 | $ 500 | 3 | $ 200 |
|
| E: Schedule Classes | 1 | $ 550 | 2 | $ 300 |
|
- Find the crash cost per day for each activity, enter in the table above
- Which activity should be crashed to meet a project deadline of 10 days (assume partial crashing is allowed for all activities)
- Find the new cost.