Question: Project on-hand inventory? MPS quantity? MPS start? Complete the MPS record below for a single item. (Enter your responses as integers. A response of O

Project on-hand inventory? MPS quantity? MPS
Project on-hand inventory?
MPS quantity?
MPS start?
Complete the MPS record below for a single item. (Enter your responses as integers. A response of "O" is equivalent to being not applicable.) Item: A Order Policy: 100 units Lead Time: 1 week February January Quantity on Hand: 75 Week 3 4 8 1 60 2 65 5 50 6 50 7 55 60 50 50 40 15 80 0 30 75 0 0 Forecast Customer orders (booked) Projected on-hand inventory MPS quantity