Question: project organization has one PC that is capable of generating the designs that their clients study before accepting their bid. The organization is currently in
project organization has one PC that is capable of generating the designs that their clients study before accepting their bid. The organization is currently in the midst of three proposal projects and knows which proposed project is most profitable. All other work to be done, both before and after the PCis used, is scheduled such that it flows to the PC and keeps it busy. Resourses used after this step are less critical; so while the subsequent work and resources are important, they aren't viewed with the same importance as the workstation. This is an example of: Subordinate the system to the constraint Identify the constraint Exploit the constraint. Elevate the constraint