Question: PROJECT PERFORMANCE ANALYSIS Highway Project Task: Build 6 0 miles of highway over a period of one year. Budget Data: 5 miles per month at

PROJECT PERFORMANCE
ANALYSIS
Highway Project
Task:
Build 60 miles of highway over a period of one year.
Budget Data:
5 miles per month at $500,000 per mile.
Assumptions:
Planned linear accomplishment of work.
All work is measurable except Program Management/Support, which is LOE.
No work in process at end of month.
Latest Performance Reports:
See the Monthly Performance Data Table and Integrated Program Management Report (IPMR) for
Month 7 that follow this page.
Calculate the:
Schedule Variance Percentage (SV%)
Cost Variance Percentage (CV%)
Cost Performance Index - Efficiency )E
Cost Performance Index - Productivity )P
Schedule Performance Index (SPI)
Months ahead or behind schedule
Percent Complete
Percent Spent
To Complete Performance Index (TCPI)
Independent Estimate at Completion (IEAC)
Estimated Completion Date (in months)(ECD)
Average Performance Rate Required to achieve the ECD
 PROJECT PERFORMANCE ANALYSIS Highway Project Task: Build 60 miles of highway

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!