Question: Project Planning ( 3 0 points ) Given the tasks with their duration and dependency Task Immediate predecessor Time ( weeks ) A - 1

Project Planning (30 points)
Given the tasks with their duration and dependency
Task
Immediate predecessor
Time (weeks)
A
-
1
B
-
2
C
A, B
3
D
B
1
E
C
3
F
C,D
2
G
E, F
4
Work alone to do the following:
a) Build the Activity On Node Network to compute the ES, EF, LS and LF
b) Compute the Slack Time
c) Determining the Critical Path
d) Determine the project duration

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!