Question: Project Planning ( 3 0 points ) Given the tasks with their duration and dependency Task Immediate predecessor Time ( weeks ) A - 1
Project Planning points
Given the tasks with their duration and dependency
Task
Immediate predecessor
Time weeks
A
B
C
A B
D
B
E
C
F
CD
G
E F
Work alone to do the following:
a Build the Activity On Node Network to compute the ES EF LS and LF
b Compute the Slack Time
c Determining the Critical Path
d Determine the project duration