Question: Project Planning, Scheduling and Control for engineers 8. A schedule performance Index SP1 of 0.76 maand: 1. you are 76% over budget. 2. you are

Project Planning, Scheduling and Control for engineers

Project Planning, Scheduling and Control for

8. A schedule performance Index SP1 of 0.76 maand: 1. you are 76% over budget. 2. you are ahead of schedule. 3. you are only progressing at 76 percent of the raic originally planned. you are only progressing at 24 percent of the rale originally planned. 4. = 8. 6 If earned valuw EV = 350, actual cost AC = 400, planned valu PV = 325, what la coet verlenco CV? 1.350 2.-75 3.400 4.-50 so 10. What is the Total Float and the Free Float for Activity F? In the figure shown, a the free float is equal ........ b the total float is equal Start 888888 6:66::8 $168 11. What is the Total Float and the Free Float for Activity J?In the figure shown a the free float is equal ........ b the total float is equal a 12 You are working on the project of painting of your house. You Identify a dependency that the painting of roof should begin only after two days of completion of painting of walle. This is an example of Lag b Lead Slack d Float 13. 4. Percent complete can be based on which of the following? a. % of work quantities in place c. a, b, c, ord b.% of time expended f.a or b c. % of budget expended g. a, b, orc d.% of resources used h. a orc

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!