Question: Project S requires an initial outlay at t = 0 of $14,000, and its expected cash flows would be $4,000 per year for 5 years.
Project S requires an initial outlay at t = 0 of $14,000, and its expected cash flows would be $4,000 per year for 5 years. Mutually exclusive Project L requires an initial outlay at t = 0 of $25,500, and its expected cash flows would be $12,850 per year for 5 years. If both projects have a WACC of 13%, which project would you recommend?
Select the correct answer.
a. Project S, since the NPVS > NPVL.
b. Both Projects S and L, since both projects have IRR's > 0.
c. Neither Project S nor L, since each project's NPV < 0.
d. Project L, since the NPVL > NPVS.
e. Both Projects S and L, since both projects have NPV's > 0.
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts
