Question: Project S requires an initial outlay at t = 0 of $16,000, and its expected cash flows would be $5,500 per year for 5 years.
Project S requires an initial outlay at t = 0 of $16,000, and its expected cash flows would be $5,500 per year for 5 years. Mutually exclusive Project L requires an initial outlay at t = 0 of $47,000, and its expected cash flows would be $11,200 per year for 5 years. If both projects have a WACC of 12%, which project would you recommend?
Select the correct answer.
| |||
| |||
| |||
| |||
|