Question: Project S requires an initial outlay at t = 0 of $12,000, and its expected cash flows would be $7,000 per year for 5 years.
Project S requires an initial outlay at t = 0 of $12,000, and its expected cash flows would be $7,000 per year for 5 years. Mutually exclusive Project L requires an initial outlay at t = 0 of $50,000, and its expected cash flows would be $12,050 per year for 5 years. If both projects have a WACC of 16%, which project would you recommend?
Select the correct answer.
| |||
| |||
| |||
| |||
|