Question: Project S requires an initial outlay at t = 0 of $18,000, and its expected cash flows would be $4,500 per year for 5 years.
Project S requires an initial outlay at t = 0 of $18,000, and its expected cash flows would be $4,500 per year for 5 years. Mutually exclusive Project L requires an initial outlay at t = 0 of $44,000, and its expected cash flows would be $14,200 per year for 5 years. If both projects have a WACC of 12%, which project would you recommend?
Select the correct answer.
a. Project L, since the NPVL > NPVS
b. Neither Project S nor L, since each project's NPV < 0
c. Both Projects S and L, since both projects have NPV's > 0
d. Both Projects S and L, since both projects have IRR's > 0
e. Project S, since the NPVS > NPVL
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts