Question: Project Scenario GSM Software Development Company received a contract to design and install a customer accounting information system from a large Utility Company. The Project
Project Scenario
GSM Software Development Company received a contract to design and install a customer accounting information system from a large Utility Company.
The Project manager has identified four types of resources, Analyst, Programmer, UI designer and Database designer to be used in the project.
Following the table below which contains the project tasks, their precedence relationships, durations, and required resources, develop a project schedule for the project plan.
tabletableTaskLabelTask Name,tableDurationWEEKSPredecessor,tabletableAnalysttableProgrammertabletableUIdesigner