Question: PROJECT SCHEDULING PROBLEM CPM Two brothers have purchased a small lot in the center of town where they intend to build a gas station. The

PROJECT SCHEDULING PROBLEM CPM Two brothers have
PROJECT SCHEDULING PROBLEM CPM Two brothers have
PROJECT SCHEDULING PROBLEM CPM Two brothers have purchased a small lot in the center of town where they intend to build a gas station. The station will have two pumps, a service area for water and tire maintenance, and a main building with restrooms, office and cash register area. Before they begin excavating the site, the local authorities must approve the location for a gasoline station and be certain that the placement of the storage tanks will not interfere with water, gas, and electric lines that are already in place. Once the site has been approved, the excavation can begin. After excavation, the three primary parts of the construction can begin: laying in the gasoline tanks, building the water and tire service area (including installation of the air compressor), and constructing the main building. The surfacing can begin after all building is completed. After surfacing, the site must be cleaned and the station's signs erected. However, before the station can open for business, the air compressor must be inspected, tested, and approved. The activities and the time required for each of them are as follows: Activity Time Required (weeks) A: Obtain site approval B: Begin site excavation C: Place and secure gasoline tanks D: Install gasoline pumps E: Connect and test gasoline pumps F: Construct service area G: Install and connect water and air compressor H: Test compressor 1: Construct main building including the rest rooms, the office, and the cash register area J: Install plumbing and electrical connections in the main building K: Cover tanks and surface the area L: Clean site M: Erect station signs 4 2 3 3 1 2 3 1 5 3 4 2 1 a) Based on the description of the project, determine the activity precedence relationships and develop a network for the project. b) Determine the critical path and the earliest and the latest starting and finishing times for each activity. c) Draw the Gantt chart for this project based on earliest limes. d) Suppose that the air compressor fails to function correctly and must be replaced. It takes two weeks to obtain another compressor and test it. Will the project necessarily be delayed as a result? e) List the activities that must be completed by the end of the 15h week in order to guarantee that the project is not delayed. PROJECT SCHEDULING PROBLEM CPM Two brothers have purchased a small lot in the center of town where they intend to build a gas station. The station will have two pumps, a service area for water and tire maintenance, and a main building with restrooms, office and cash register area. Before they begin excavating the site, the local authorities must approve the location for a gasoline station and be certain that the placement of the storage tanks will not interfere with water, gas, and electric lines that are already in place. Once the site has been approved, the excavation can begin. After excavation, the three primary parts of the construction can begin: laying in the gasoline tanks, building the water and tire service area (including installation of the air compressor), and constructing the main building. The surfacing can begin after all building is completed. After surfacing, the site must be cleaned and the station's signs erected. However, before the station can open for business, the air compressor must be inspected, tested, and approved. The activities and the time required for each of them are as follows: Activity Time Required (weeks) A: Obtain site approval B: Begin site excavation C: Place and secure gasoline tanks D: Install gasoline pumps E: Connect and test gasoline pumps F: Construct service area G: Install and connect water and air compressor H: Test compressor 1: Construct main building including the rest rooms, the office, and the cash register area J: Install plumbing and electrical connections in the main building K: Cover tanks and surface the area L: Clean site M: Erect station signs 4 2 3 3 1 2 3 1 5 3 4 2 1 a) Based on the description of the project, determine the activity precedence relationships and develop a network for the project. b) Determine the critical path and the earliest and the latest starting and finishing times for each activity. c) Draw the Gantt chart for this project based on earliest limes. d) Suppose that the air compressor fails to function correctly and must be replaced. It takes two weeks to obtain another compressor and test it. Will the project necessarily be delayed as a result? e) List the activities that must be completed by the end of the 15h week in order to guarantee that the project is not delayed

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!