Question: project # SR 5 5 H has finished 1 3 months of a 2 4 month planned schedule. you are given the matrix below: What

project # SR
5
5
H has finished
1
3
months of a
2
4
month planned schedule. you are given the matrix below: What is the project status? Budget for the program
=
$
5
5
,
0
0
0
EV
(
cumulative
)
=
$
2
7
,
5
0
0
AC
(
Cumulative
)
=
$
2
5
,
2
2
5