Question: Project team : Project Manager, Business Analyst, UI/UX, Developer, Tester, vendor Imagine you are the Project Manager handling 5 projects at the moment and one

Project team : Project Manager, Business Analyst, UI/UX, Developer, Tester, vendor Imagine you are the Project Manager handling 5 projects at the moment and one of the project is to implement an expense claim system for an organization with 100 users. Based on the information below, create a budget plan for your project. ID Task Immediate predecessor Expected Duration (days) A Gather business requirement 5 B Create software specification A 5 C User interface design B 5 D Develop SW B 20 E Debug D 5 F Prepare draft manual D 5 G Meet with client (Demo) F 5 H UAT E,G 20 I Make modifications H 10 J Finalize manual I 10 K User Training I 5 L Deployment communication E, G 2

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Accounting Questions!