Question: project with higher than average risk offers an expected return of 18%. Which statement is correct if the company's opportunity cost of capital is 12%
project with higher than average risk offers an expected return of 18%. Which statement is correct if the company's opportunity cost of capital is 12% and the project's opportunity cost of capital is 15%?
A) Project NPV is positive; it should be accepted.
B) Project NPV is negative; it should be rejected.
C) Project NPV is positive but it should be rejected.
D) Project NPV is negative but it should be accepted.
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts
