Project Year 0 Year 1 Year 2 Year 3 Year 4
A -$101 $25 $28 $38 $52
B -$101 $52 $38 $28 $22
a. What is the NPV of each project at your cost of capital? (Round to two decimal places.)
The NPV for project A is $_____ million.
The NPV for project B is $______million.
b. What is the IRR of each project?
(Round to two decimal places.)
The IRR for project A is _____%
The IRR for project B is _____%
c. At what cost of capital are you indifferent between the two projects?
(Round to two decimal places.)
You will be indifferent if the cost of capital is _____%
d. What should you do?
Given your cost of capital, which project would you choose?(Select the best choice below.)
A. You should invest in project Upper B, as it has the higher IRR.
B. You should invest in project Upper A, as it has the higher NPV.
C. You should invest in project Upper A, as it has the higher IRR.
D. You should invest in project Upper B, as it has the higher NPV.

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Finance Questions!