Question: Project_Q2 The table below provides the required information for Project Questions Q2, Q3, Q4, and Q5. Task. No Description Predecessor Duration in Days 1 Obtain
Project_Q2 The table below provides the required information for Project Questions Q2, Q3, Q4, and Q5. Task. No Description Predecessor Duration in Days 1 Obtain Authorization 5 2 Hire Scrum Expert 1 25 3 Organize Training 2 10 4 Coordinate Logistics 2 20 5 Announce Training 3 , 4 20 6 Perform Training 5 5 What is the overall project duration? Group of answer choices 85 days 80 days 77 days 75 days