Projects encounter risks across its life cycle that have to be identified and responses planned for. As you identify
potential project risks, you categorise them. One such category is an 'external-unpredictable risk ?. Which of the
following is not an external-unpredictable risk?
A. Inflation
B. Changes in government regulations
C. Unexpected environmental side effects
D. Natural hazards