Question: Projects that require a more rigid and formal change process are best suited to use which type of approach? Question 1 options: Predictive Phase Gate
Projects that require a more rigid and formal change process are best suited to use which type of approach?
Question options:
Predictive
Phase Gate
Hybrid
Adaptive