Question: Proposed Process Change 2 : A second proposal would hire an additional worker to join the existing five workers. Three workers would be trained and
Proposed Process Change : A second proposal would hire an additional worker to join the existing five workers. Three workers would be trained and resourced to carry out jobs made up of the current Tasks and ; similarly, the other three workers would each be trained and resourced to complete the work of the current Tasks and
What is the cycle time of the process in minutes per unit
What is the output rate in units per hour for the process ie process capacity
What is the labour productivity in units per labour hour of the process?
What is the percent change in labour productivity between the current and the second proposed process design?