Question: provide an answer for these three questions: QUESTION 1 7 Your team has made a list of all the risks identified by various stakeholders using
provide an answer for these three questions: QUESTION
Your team has made a list of all the risks identified by various stakeholders using several methods. You then made sure the risks are understood & triggers identified. You just completed working with your stakeholders to determine ways to mitigate each of the risks. What have you done wrong?
a
More people should be involved in the plan risk responses.
b
Triggers are not identified until the identify risks process.
c
You should have created workarounds
d
You should have waited until the perform qualitative risk analysis process to get the stakeholders involved.
points
QUESTION
You have just determined that you need to transfer a risk. In which of the following risk management processes are you?
a
Identify risks
b
Plan risk responses
c
Monitor and control risks
d
Perform quantitative risk analysis
points
QUESTION
Which of the following accurately describes risk in project management?
a A risk may impact the project in a positive or negative way.
b Some projects have no risks.
c Risk assessment should remain objective and uninfluenced by stakeholder priorities.
d Project managers should always be risk averse
points
QUESTION
You are the project manager on a multiyear facilities development project. Significant spring rains caused major flooding that caused power outages and the loss of all project records not stored on your laptop. What should have been done to prevent this problem?
a
Plan for a larger management reserve.
b
Approve a larger contingency reserve.
c
Maintain the records outside a flood plain
d
Monitor the weather and have a contingency plan.
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock