Question: Provide an Answer in MS Excel? An IT support group at a university has seven projects to complete. The time in days and project deadlines

Provide an Answer in MS Excel?
An IT support group at a university has seven projects to complete. The time in days and project deadlines are shown below. Project 2 3 4 1 5 6 7 Time 4 12 16 9 15 8 Deadline 12 24 |60 28 24 36 48 Sequence the projects to minimize the average lateness. a. b. Sequence the projects to minimize the average tardiness. Compare these solutions to the SPT and EDD rules. C. et An IT support group at a university has seven projects to complete. The time in days and project deadlines are shown below. Project 2 3 4 1 5 6 7 Time 4 12 16 9 15 8 Deadline 12 24 |60 28 24 36 48 Sequence the projects to minimize the average lateness. a. b. Sequence the projects to minimize the average tardiness. Compare these solutions to the SPT and EDD rules. C. et