Question: Provide the answer with a full brief explanation A7-1 (Static) Given the project information... Given the project information in the following table, what is the
Provide the answer with a full brief explanation 
A7-1 (Static) Given the project information... Given the project information in the following table, what is the probability of completing the National Holiday Toy project in 93time units? Hint: Use the =NORM.S.DIST(z, TRUE) function in Excel to compute the probability. (Carry at least 3 decimal places in all intermediate calculations and the Z value. Enter your final probability answer to 3 decimal places.)
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts