Question: provide the problem statement and background, the solution approach, create a present - state VSM , Analyze the four problems with the present - state

provide the problem statement and background, the solution approach, create a present-state VSM, Analyze the four problems with the present-state VSM?, and Create a future-state VSM (The future-state map should address each of the six problems identified in Question. The Question is The 200,000 sq. ft. facility shown in Figure 1 has been manufacturing flanges in Indianapolis, IN for the past 50 years.
Figure 1. Flange Factory, Flanges are bolted, steel plates used to connect pipes with one another. Manufacturing of flanges consists of five operations: (1) hot forging; (2) batch normalizing; (3) turning; (4) drilling; and (5) assembly. As is typical of a facility of this age, all production assets are fully depreciated.
Value Stream Mapping at an Indianapolis, IN Flange Manufacturer
To address some issues within the facility, senior management has asked for a present-state VSM covering all aspects of flange manufacturing, from incoming raw materials to outgoing finished products. Management has likewise asked for a future-state VSM to address any issues uncovered.
The distribution centers standing 12,000-piece weekly production order is issued to the factory through SAP (enterprise resource planning software). The logistics department arranges for pick-up from the factorys finished product warehouse every Friday at the end of the production shift for evening delivery to Muncie. Recently, the logistics department at the distribution center has been complaining about excessively long manufacturing lead times as compared to the industry standard of two weeks. Incoming Logistics
The factory manufactures flanges from steel bars (Figure 3). Each bar weighs 94 kg and costs USD 88(excluding delivery fee). The steel bar supplier is located in Gary, IN. The bar vendor is capable of delivering every week, every two weeks, every three weeks, and so forth. The purchasing department issues a purchase order (PO) through SAP for 1,000 steel bars to be delivered every four weeks. The transportation cost is USD 300 per truckload. A single truck can carry 20,000 kgs of bar.
Figure 3. Steel Bars Made at Supplier Every week, the purchasing department at the flange manufacturer sends a USD 700 PO for a single pallet of 25,000 screws. Of that amount, USD 500 is for screws (i.e., USD 0.02/screw). The courier charges USD200 per pallet delivered. Pallets can hold up to 25,000 screws. The distributor, which is located in Evansville, IN, is only able to offer weekly pallet shipments to Indianapolis out of its warehouse. Presently, there are 1,000 steel bars and 100,000 screws in the raw materials warehouse at the factory. The carrying cost of steel bar inventory is 3% of the total amount spent on bars in inventory (excluding transportation cost). The annual carrying cost of screws is, likewise, 3% of the total amount spent on screws inventory
(excluding transportation costs). Delivery of bars from the vendor in Gary has been an issue. On average, shipments are one day late. Screws, however, are always delivered on time.
Value Stream Mapping at an Indianapolis, IN Flange Manufacturer
Manufacturing Operations
The flange-making factory is open 50 weeks per year, five days per week, eight hours per shift, and three shifts per day. The production office does not plan for processes to be running for all eight hours in a shift. Actual production time available is assumed to be at 85% overall equipment efficiency (OEE).
Hot Forging
In the hot forging department, one flange is made from 2 kg of bar stock (not including scrap). Forging involves three steps: (1) induction heating bar to 300\deg C (see Figure 5); (2) shearing bar into segments of appropriate length; and then (3) closed die shaping segments. The factorys two bar forging lines were purchased for USD 500,000 each. Each line is run by a single operator and runs a 90-second cycle time. Uptime in the forging department averages 94%. Scrap is 3%. Batch Normalizing
After forging, steel grains making up the flange are too distorted for machining. Parts must be cooled for a day and then transferred into steel tubs for a batch heat-treating process called normalizing. Approximately 200 parts fit into a tub. The normalizing furnace (as shown in Figure 6) was purchased for USD 1,000,000.
Depreciation was done on a straight-line basis over 10 years, as is standard at the facility. One person operates the furnace and is capable of processing 250 kg per hour. Uptime is 100%. After normalizing, parts must be placed in a holding area for at least one day to allow them to reach room temperature for subsequent machining. Turning
Turning is done on the opposite side of the factory from normalizing and drilling. This is because only the side of the factory where turning is located is plumbed for turning coolant. The turning department has three machining centers (Figure 7), each operated by a single machinist. One turning center costs USD 250,000. Cycle t

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!