Question: Provide your solutions on additional sheets. Hand drawn are fine as long as they are legible. Draw the network diagram for the following set of

Provide your solutions on additional sheets. Hand drawn are fine as
long as they are legible.
Draw the network diagram for the following set of tasks, durations and
precedence.
Task Duration(weeks) Predecessors
A 3-
B 4 A
C 2-
D 2-
E 5 B,C
F 3 D
G 2 E,F
H 4 B
I 4 G,H
a. What is the project duration?
b. What is the critical path?
c. How much slack is associated with each task (A-I)?

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!