Question: PS: (5.15 is the wrong answer, just forgot to erase it :)) A public utility intends to buy a turbine as part of an expansion

PS: (5.15 is the wrong answer, just forgot to

PS: (5.15 is the wrong answer, just forgot to erase it :))

A public utility intends to buy a turbine as part of an expansion plan and must now decide on the number of spare parts to order. One part, no. X135, can be purchased for $80 each. Carrying and disposal costs are estimated to be 100 percent of the purchase price over the life of the turbine. A stockout would cost roughly $105,000 due to downtime, ordering, and "special purchase" factors. Historical records based on the performance of similar equipment operating under similar conditions suggest that demand for spare parts will tend to approximate a Poisson distribution with a mean of 4.2 parts for the useful life of the turbine. Use Table C. a. What is the optimal number of spares to order? Optimal number of spares b. Carrying no spare parts would be the best strategy for what range of shortage cost? (Round your answer to 2 decimal places.) Shortage cost Cs

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!