Question: PS . 7 4 Bell computer is planning to launch a new high - end server. Nine steps or tasks are required to assemble this

PS
.
7
4
Bell computer is planning to launch a new high
-
end server. Nine steps or tasks are required to assemble this computer. Daily demand is expected to be
8
5
units and there are three
8
-
hour shifts available each day to meet this production quota.
Task Req'd Time
(
in minutes
)
Predecessor
A
1
1
None
B
1
3
A
C
6
B
D
4
B
E
1
6
A
F
3
C
,
D
G
9
F
H
1
4
E
I
4
G
,
H