Question: Put the following framing phase construction task in the correct construction order Second sub - floor decking Roof decking Floor joist Sill plates Walls and

Put the following framing phase construction task in the correct construction order
Second sub-floor decking
Roof decking
Floor joist
Sill plates
Walls and beams
Trusses
First sub-floor decking