Question: Put the steps used in the parallel method of resource constrained smoothing into their correct order. Instructions Assign resources to the activity with the minimum
Put the steps used in the "parallel method" of resource constrained smoothing into their correct order.
Instructions
Assign resources to the activity with the minimum amount of slack, unless there is a tie
Assign resources to the activity with the smallest activity identification number.
Assign resources to the activity with the smallest duration, uniess there is a tie.