Question: PV Unit Technical Cost (PV UTC) is the ............ divided by the ..........? - choose 1 answer Group of answer choices NPV divided by PV
PV Unit Technical Cost (PV UTC) is the ............ divided by the ..........? - choose 1 answer
Group of answer choices
NPV divided by PV Production
(PV capex + PV opex) divided by PV Production
(PV capex + PV opex) divided by PV Revenue
NPV / PV Capex
PV Capex / PV Opex
None of the above