Question: Q 1 0 . Your project team is complaining that the acceptance criteria of their work result are unclear and ask you to provide clarification

Q 10. Your project team is complaining that the acceptance criteria of their work result are unclear
and ask you to provide clarification with the customer. You arrange a meeting, and several criteria
are identified.
The product acceptance criteria should now be laid down in which documents? (Choose 2)35
a. Project scope statement
b. Work breakdown structure
c. Resource assignments
d. Project scope management plan
e. An addendum to the project contract