Question: Q 1 ) ( 4 0 Marks ) A ) Answer the following Statements with True or false and correct the False One: ( 2

Q1)(40 Marks)
A) Answer the following Statements with True or false and correct the False One: (20 Marks)
1- If it is not possible to develop a byproduct, then scrap materials should be separated to obtain top scrap prices.
2. Using a manufacturing process that produces components to the final shape can minimize material use, reduce scrap, minimize secondary processing.
3- Material Handling is only considering the transportation of materials
4. We should use static holds rather than dynamic motions
5- Design for maximum is considered the most expensive type of design.
6. It is recommended to begin and end motions with both hands incrementally
7. Industrial Engineer use operation analysis to study all Productive elements in a certain operation, and the non productive elements is not necessarily at this stage.
8- To elimirate an operation, Analyst should ask the following question "can we purchase this item in less cost from outside".
a. Providing an ample space for each bit of information is considered one of the main points in the Tolerance and specifications steps of the operation analysis
10. Using the Material more cconomically means that the salvage value should not be taken into consideration when analyzing materials
11- The time utilized by the manufacturing process is divided into four steps: Inspection, Inventory control and planning, setup operation, and in process manufacturing
12.- There is one type of layout that tends to be the best
13- Shape, texture, and size coding are used to facilitate touch identification of controls
14. Design for adjustability is typically implies that a specific design feature is a limiting factor in determining either the maximum or minimum value will be recommended
15- Decision tables are simple way to expand the evaluation of alternatives by applying numbers and forming payoff matrix.
16. Handle lengths of tools should be designed to be a maximum of 4 inches.
17. Methods engineering Simplifies work to increase productivity and reduce cost
18. Work Design Fits Work to the operator to increase his productivity
19. Gentt Charts, gang process charts are used to select the project to be developed
20- In operation process chart we use only 5 symbols (operation, transportation, storage, delay, and inspection
\table[[No.,True,False,correction],[1.,,,],[2.,,,],[3.,,,],[4.,,,],[5.,,,],[6.,,,],[7,,,],[8.,,,],[9.,,,],[10.,,,],[11.,,,],[12.,,,],[13.,,,],[14.,,,],[15.,,,],[16.,,,],[17.,,,],[18.,,,],[19.,,,],[20.,,,]]
 Q1)(40 Marks) A) Answer the following Statements with True or false

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!