Question: Q . 1 ( a ) Prepare the detailed estimate of road side masonry dust bin given in Figure below ( All dimensions are in

Q.1(a) Prepare the detailed estimate of road side masonry dust bin given in Figure below (All dimensions are in cm until specified otherwise).
General specifications are:
(i) Concrete in foundation and under floor: 1:2:4 cement concrete (B)(ii) Masonry work: All masonry work in 1st class brick work in 1:6 cement and local sand mortar (C),(iii) Flooring: 40mm thick 1:2:4 cement concrete (D),(iv) Plastering cement sand mortar in proportion of 1:6 all around (inside and outside walls)(E) and (v) Finishing: Two coats snowmen painting on outside walls (F),(vi) Iron door gauge 18,(G). Adopt suitable rates from 'Schedule of Rates' as given in book (increase the rate by 400%) or CPWD rates.
(b) Calculate the duration of each activity, and prepare A-O-N for one dustbin.
(c) Prepare LoB if 1000 dustbins are to be completed within 3 months. Assume 8 working hours in a day; 5 working days in a week and 4 weeks in a month. Buffer: 2 days. Take Man hours for different activities as Earthwork A : 10, B : 25, C : 40, D : 20, E : 80, F: 40, and G: 20. B, C... are mentioned in part (a) above.
Q . 1 ( a ) Prepare the detailed estimate of road

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Civil Engineering Questions!