Question: Q 1 . Based on the model above and assumptions below, calculate the cycle time in seconds. Assume that, on average and including waiting time,

Q1. Based on the model above and assumptions below, calculate the cycle time in seconds.
Assume that, on average and including waiting time, Take customers order and Process payment task each takes 30 seconds. The Cook fries in fryer task takes 3 minutes, the Grill patties task takes 2 minutes, the Place buns in toaster takes 40 seconds, and the Assess quality task takes 3 minutes. All other tasks take 5 seconds.
In 30% of the cases, fries are not ready and will need to be cooked.
In 20% of the cases, the patties and buns are not ready and will need to be cooked.
In 5% of the cases, the quality of the patties and buns are not acceptable and will have to be prepared and cooked again.
 Q1. Based on the model above and assumptions below, calculate the

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!