Question: Q . 1 Set. ( B ) Calculate the overall equipment effectiveness of the production machine with the following data. [ 6 ] S No

Q.1Set. (B) Calculate the overall equipment effectiveness of the production machine with the following data. [6]
S No Planned Shutdown Hours or Count Gross Time 24 Hours (or Minutes)
1 No production, Breaks, Shift change 2.66 Hours Meeting and Shift Change
2 Planned Maintenance 2.00 Hours Monthly Plant Maintenance
3 Waiting for Operator 1.66 Hours
4 Failure or breakdowns 1.33 Hours Mechanical drive coupling
5 Minor Stops 10 events Jams!
6 Reduced Speed 100 Units produced Vs.167 Units planned production Design rate: 12.5 Units/hour
7 Yield/ Transition 5 count Startup and adjustment related
8 Defects, rework 1 count
9 Scrap product/output 2 count Waste, non-salvageable
10 Material Flow: output (Kanban full)0 Output not needed, no room in queue
11 Start up and Adjustment 1 Hour 1st shift on Monday
12 Tooling and Part Change 0.83 Hour Screw station bits
13 Material flow : Input ( No Material)0 Waiting for raw materials
14 Setup and changeover 1.16 Hours 2 size changes

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!