Question: Q 1 : ( True or False ) Force majeure events are typically considered non - compensable delays under normal circumstances, which allow the contractor
Q: True or False Force majeure events are typically considered noncompensable delays under normal circumstances, which allow the contractor to recoup the lost time but not the costs for extended overhead