Question: Q 1 . Your team is working on a Work Breakdown Structure for the bike lane / road expansion project. The highest level of the

Q1. Your team is working on a Work Breakdown Structure for the bike lane / road expansion project.
The highest level of the WBS is "Complete Bike Lane Addition". The WBS is started below:
a) List 3-5 work packages under 1.0.
b) Do you think 2.0 is complete? Why or why not? Hint: What rule are you checking for?
c) Your colleague looks at this WBS and points out that the order of 2.1 and 2.3 should be
switched. Is this necessary?