Question: Q 18 To complete a contract for fitting out a new shop in time for its opening, a refurbishment company has employed three temporary painters

Q 18

To complete a contract for fitting out a new shop in time for its opening, a refurbishment company has employed three temporary painters for 10 days at 45 per day and moved two carpenters who are paid 70 per day from another job for three days. The penalty for late completion of the shop is 300 but the delay to the carpenters current job will only cost 150. What are the relevant costs?

a) 1,770
b) 1,500
c) 1,650
d) 1,800