Question: Q 2 ( 5 0 points ) The network diagram of a project is shown below. ( a ) Use two - pass method to
Q points The network diagram of a project is shown below.
a Use twopass method to determine the critical path you can show the different times in the above diagram points
b What is the project duration? points
c What is the slack time of activity F points
d Activities A B C D can be crashed. The normal time, crash time, normal cost and crash cost are shown in the table below. What is the daily crash cost of each activity? points
e The project needs to be completed in days. How can you achieve this goal at minimum cost? Please report your crashing steps in the table below. The table size does not imply the number of steps that will be needed. points
tabletableNormal timedaysNormal Cost $Crash time daysCrash Cost $tableDaily Crash Cost$dayABCD
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock