Question: Q 2 7 - 1 . png Q 2 7 - 1 . png To avoid delaying the completion of the project, activity C has
Qpng
Qpng
To avoid delaying the completion of the project, activity C has to start no later than day
The completion time of the project is days.
The critical path of the project is ABDH
If activity F is completed on day the progress of the project will NOT be delayed.