Question: Q 2 , PERT 5 marks ) As a new project that you need to manage, you were not able to get exact estimates for
Q PERT marks As a new project that you need to manage, you were not able to get exact estimates for the activity durations. Instead, you were able to get three estimates for each activity: optimistic, most probable, and pessimistic as shown in the table below.
tableActivityDuration daysPredecessors,tableExpectedtimeSigma,SigmaOptimistic,tableMostprobablePessimistic,,,,ABCDA BEB CFD E
a For each activity, calculate its expected time and its standard deviation.
b Identify all paths in this project.
c For each path, calculate the path duration and its standard deviation.
d What is the probability that path A D F finishes in more than days?
e Your manager is asking you for a time estimate for path A D F such that you are sure that this path would finish in less than this time., PERT As a new project that you need to manage, you were not able to get exact estimates for the activity durations. Instead, you were able to get three estimates for each activity: optimistic, most probable, and pessimistic as shown in the table below
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock