Question: Q 2 table [ [ Job , table [ [ Processing Time ] , [ Machine 1 ] ] , table [

Q2
\table[[Job,\table[[Processing Time],[Machine 1]],\table[[Processing Time],[Machine 2]],],[A,5,10,],[B,2,7,],[C,12,4,],[D,13,9,],[E,5,3,],[F,6,11,],[,,,]]
A- Find the optimum sequencing using Johnson rule, draw the time line to completion, Calculate the amount of WIP time
B- Randomize the sequencing and redo step A.
C- Comment on the findings
 Q2 \table[[Job,\table[[Processing Time],[Machine 1]],\table[[Processing Time],[Machine 2]],],[A,5,10,],[B,2,7,],[C,12,4,],[D,13,9,],[E,5,3,],[F,6,11,],[,,,]] A- Find the optimum sequencing