Question: Q 24 The difference between the cost baseline and the cost budget can be BEST described as the Select one: a. Management reserves b. Cost

Q 24 The difference between the cost baseline andQ 24 The difference between the cost baseline and

Q 24 The difference between the cost baseline and the cost budget can be BEST described as the Select one: a. Management reserves b. Cost account c. Project cost estimate O d. Contingency reserves Q2 The difference between EV and the PV is referred to as the Select one: O a. Schedule variance b. Estimate of completion c. Actual cost of the work performed O d. Cost variance