Question: Q 3 . 2 ( Algo ) Process Analysis with Multiple Flow Units [ 3 . 6 ] Consider a process consisting of five resources
QAlgo Process Analysis with Multiple Flow Units
Consider a process consisting of five resources that are operated eight hours per day. The process works on three different products, A B and C:
Resource Number of Workers Processing Time for A Minutes per Unit Processing Time for B Minutes per Unit Processing Time for C Minutes per Unit
Demand for the three different products is as follows: product A units per day; product B units per day; and product C units per day.
What is the demand per hour and the implied utilization as a percentage at each resource? What is the bottleneck?
Note: Round "Demand per hour" to decimal places and Implied Utilization" to decimal place.