Question: Q 3 5 : A formal CPM analysis for a projects shows the planned costs to date are $ 8 5 , 0 0 0

Q35: A formal CPM analysis for a projects shows the planned costs to date are $85,000 and the accounting department reports charges to the job of $95,000 to date is $70,000, the cost and schedule status of the project are most nearly:
A. Ahead of schedule and over budget
B. Behind schedule and over budget
C. Ahead of schedule and under budget
(D) Behind schedule and under budget