Question: Q 3 5 : A formal CPM analysis for a projects shows the planned costs to date are $ 8 5 , 0 0 0
Q: A formal CPM analysis for a projects shows the planned costs to date are $ and the accounting department reports charges to the job of $ to date is $ the cost and schedule status of the project are most nearly:
A Ahead of schedule and over budget
B Behind schedule and over budget
C Ahead of schedule and under budget
D Behind schedule and under budget