Question: Q 3 . ( 5 MKS ) : Assume we're halfway through a year - long project that has a total budget of $ 1

Q3.(5 MKS): Assume we're halfway through a year-long project that has a total
budget of $100,000. The amount budgeted through this six-month mark is
$55,000. The actual cost through this six-month mark is $45,000.Al
calculation must be shown in the solution.
Calculate the Actual Cost (AC), planned Value(PV),.amed Value
(EV).
Calculate the Schedule Performance Index (SPI) und SPI % Determine
if the project is behind or ahead schedule.
Calculate the Cost Performance Index (CPI) an 1 CPI %.1 etermine if the
Project is over budgeted or under budgeted.
Determine the outcome of the project in terms of cost and schedule.
 Q3.(5 MKS): Assume we're halfway through a year-long project that has

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Databases Questions!