Question: Q 3 ( 8 marks ) : The durations and direct costs for each activity in the network of a small construction contract under both
Q marks: The durations and direct costs for each activity in the network of a small construction contract under both normal and crash conditions are given in the following table. Establish the least cost for expediting the contract. Determine the optimum duration of the contract assuming the indirect cost is day.
Where is your last three numbers of you UOB ID number for example if your ID then the indirect cost will be
Note: you cannot crash days in one time for any activity.
tableActivityPrecedence,tableNormal TimeDaystableCrash TimeDaystableNormal Cost$
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
