Question: Q - 3 . A 1 km long concrete - lined tunnel connects two reservoirs with the water surface elevation in the lower reservoir being

Q-3. A 1 km long concrete-lined tunnel connects two reservoirs with the water surface elevation in the
lower reservoir being 23m below to that in the upper reservoir. Roughness height of concrete lining is
given as 1.5mm. Determine the diameter of the tunnel if the flow has to be maintained at 2m3s. Ignore
all minor losses. Assume kinematic viscosity of water =10-6m2s.(Hint: Since this is the type 3 problem
with unknown D, start with an assumed friction factor and find D, then solve iteratively. Use Moody
Diagram from Lecture 5 or your textbook.)
Q - 3 . A 1 km long concrete - lined tunnel

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Civil Engineering Questions!