Question: Q 3 . A project team is in the process of performing the tasks shown in Table Table 1 . begin { tabular }

Q3. A project team is in the process of performing the tasks shown in Table
Table 1.
\begin{tabular}{|c|c|c|}
\hline Task & \begin{tabular}{c}
Immediate \\
Predecessor(s)
\end{tabular} & \begin{tabular}{c}
Time \\
(in days)
\end{tabular}\\
\hline a & - & 3\\
\hline b & a & 5\\
\hline c & a & 1\\
\hline d & b, c & 4\\
\hline e & b & 3\\
\hline f & e, d & 3\\
\hline g & f & 2\\
\hline h & e, d & 4\\
\hline
\end{tabular}
a) Draw the AON and AOA diagrams.
b) Find the critical path(s) and the completion time of the project.
c) Determine the total slack and free slack for each activity.
Q 3 . A project team is in the process of

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!