Question: Q 3 . Haggrun Co has two contracts in progress, the details of which are as follows. BUSI 2 1 5 8 Intermediate Corporate Reporting

Q3. Haggrun Co has two contracts in progress, the details of which are as follows.
BUSI2158 Intermediate Corporate Reporting Seminar 2
Haggrun measures satisfaction of performance obligations based on percentage of
work certified as complete.
Required:
Show extracts from the statement of profit or loss and other comprehensive income
and the statement of financial position for each contract, assuming they are both
certified as:
(1)40% complete; and
(2)36% completeHaggrun Co has two contracts in progress, the details of which are as follows.
Happy (profitable) Grumpy (loss-making)
$000 $000
Total contract revenue 300300
Costs incurred to date 90150
Estimated costs to completion 135225
Payments invoiced and received 116116
Haggrun measures satisfaction of performance obligations based on percentage of work certified as complete.
Required:
Show extracts from the statement of profit or loss and other comprehensive income and the statement of financial position for each contract, assuming they are both certified as:
(1)40% complete; and
(2)36% complete
 Q3. Haggrun Co has two contracts in progress, the details of

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Accounting Questions!